ancon

Ancon Building Products

Home
About Ancon
Products
What's New
Projects
Downloads
FAQs
Contacts
Links
Search
go

The Use of Stainless Steel
Masonry Support
Windposts
Lintels
Wall Ties & Restraint Fixings
Channel & Bolt Fixings
Tension Systems
Shear Load Connectors
Ancon Solutions to Joints
Performance Comparison
Range of Shear Connectors
Fire Protection
Installation Procedure
Stainless Steel Reinforcement
Reinforcing Bar Couplers
Reinforcement Continuity Systems
Punching Shear Reinforcement
Sections & Flooring
Special Fabrications
Refractory Fixings
Lindapter Weld-Free Steel Connectors
you are here: home > products > shear load connectors > installation procedure > dsd/dsdq shear load connectors
  Contact us  
decrease the text size increase the text size
   print page 
   site map  

DSD/DSDQ Shear Load Connectors

 submit >> 

The two part design of all Ancon shear connectors removes the need for drilling formwork on site, supporting dowel bars and fitting debonding sleeves and end caps. The installation is a fast and accurate process.


Nail the sleeve component to the shuttering ensuring that the sleeve is correctly orientated for the direction of the load. Check minimum spacings and edge distances are not exceeded. The label prevents debris from entering into the sleeve and should not be removed.


Fix the local reinforcement ensuring that the correct cover to the reinforcement is maintained. Pour the concrete to complete the installation of the sleeve component.


When the concrete has achieved sufficient strength, strike the shuttering. Puncture the label to reveal the holes for the dowels. Where Q products are used, the label should only be punctured enough to allow the dowels into the cylindrical sleeve to prevent debris entering the box section.


Position the compressible joint filler.


Push the dowel component through the joint filler until it is fully located in the sleeve component. It may be necessary to tap the dowel component to overcome the dimple that pinch holds the dowel in the sleeve and prevents dislocation when the concrete is vibrated.

Fix the local reinforcement ensuring that the correct cover to the reinforcement is maintained. Pour the concrete to complete the installation of the Ancon shear connector.



Notes

Although installation is shown for the Ancon DSD, the procedure is the same for all Ancon shear connectors.

Where deep concrete pours are proposed, the installation will require further consideration. More robust fixing of the sleeve and dowel components will be necessary, to avoid displacement during placing of the concrete.